NTPC Lara Super Thermal Power Plant
Client
NTPC Limited
Sector
Thermal Power
Duration
2023 – Present
Value
Rs. 5 Cr.
Project Overview
About This Project
Hindland Infrastructure is executing critical CHP (Coal Handling Plant) works at the NTPC Lara Super Thermal Power Plant, one of the most significant thermal energy projects in Central India. Our scope covers stacker and reclaimer erection, precision alignment, civil and structural works, and commissioning assistance for the coal handling infrastructure. This project showcases our capability to handle large-scale power-sector contracts with strict adherence to timelines, safety standards, and NTPC's quality benchmarks.
Key Highlights
Rs. 5 Cr.
Project Value
2x800 MW
Capacity
200+
Workforce Deployed
Zero LTI
Safety Record
What We Deliver
Scope of Work
Stacker & Reclaimer Erection
Complete erection of stacker and reclaimer systems including structural assembly, boom installation, and track alignment.
Alignment & Commissioning
Precision alignment of rotating equipment and commissioning assistance for CHP conveyor systems.
Civil & Structural Works
Foundation construction, embedded parts installation, and structural steel erection for CHP buildings.
Conveyor Systems
Erection and alignment of belt conveyors, transfer points, and junction towers for coal transport.
Safety Management
Implementation of NTPC safety standards including PTW systems, toolbox talks, and HSE audits.
Quality Assurance
Rigorous QA/QC protocols following NTPC specifications for welding, erection tolerances, and material traceability.
Visual Documentation
Project Gallery